The first building of the $7 billion 1901 Project is a parking garage. Before the 6,000-seat music hall and before the hotel, crews are working on the West Garage. That garage sits at Damen Avenue and Madison Street, and it has also changed. It was supposed to hold the campus's showpiece park, and now it doesn't. Changes approved in late May and a permit revision issued in August moved that park off the roof and down to street level at Damen and Adams, right next to the music hall. Block Club reported the change in September. If you live at the western edge of the West Loop, this matters more than any rendering. The project's main public space will now meet the sidewalk instead of sitting one story up.
The order of operations
Officials held the groundbreaking on June 3, 2026. Phase 1 covers about 12.3 acres of surface parking south and west of the arena and costs roughly $500 million of the total. Urbanize Chicago laid out the building sequence:
- The West Garage. It is wrapped in a one-story brick podium with storefronts and expands the United Center's lower-level loading dock. McHugh Construction is the general contractor and already held foundation and tower crane permits at the groundbreaking.
- The music hall. It sits at Damen and Adams and opens east onto a large plaza. Its design changed to a scalloped form rising from a brick base.
- The south garage. It holds retail at street level, two floors of parking, and five floors of hotel rooms above.
In June, Chicago YIMBY reported groundwork underway at the music hall and the West Garage, with the hotel site still relatively quiet. The hotel's size isn't settled in the press. Block Club and Urbanize both reported 233 rooms. The Chicago Sun-Times reported 180 keys. None of the coverage names a hotel brand.
Block Club's groundbreaking story puts the whole first phase at spring 2028. The money is in place. Urbanize, citing Crain's, reported a $125 million Wintrust loan for the first phase and some work at the arena.
Why the park came down off the roof
Earlier renderings showed people playing soccer, walking trails, and sitting on a lawn on top of the West Garage. Those images were part of the plan the City Council approved in February 2025. In late May 2026, the Chicago Plan Commission approved changes that removed that park and a pedestrian bridge from the garage. On Aug. 21, the city issued a building permit revision that took the rooftop park out. Block Club Chicago reported that the new renderings show parking on the top level.
The same May approval moved the music hall about 50 feet east, away from Damen. That freed up ground just west of the hall for a park. The renderings show people picnicking there and playing soccer and basketball. A project spokesperson explained the change in a statement to Block Club Chicago:
"After hearing from local residents and considering how the park would best serve the neighborhood in practice, we, together with our partners, have decided to refine our plans by moving the elevated park space to grade level. We are delivering the park space with a ground-level approach, which will create a more accessible, connected and welcoming public space designed to better serve our neighbors and the broader community."
The original design asked people to climb to reach the park. Urbanize's description of the first West Garage plan had visitors using a sloped outdoor path up from the street or one of three vertical access points. The new version sits on the corner. The architecture firm RIOS now describes a west park with recreational courts and programming all year.
Two numbers are still open. The January 2025 city presentation counted 25.5 acres of open space across the full plan, with 9.6 acres in Phase 1. That count came before the rooftop park was dropped, and no revised total has been published. Urbanize's June story also described a green roof on the south garage. None of the September coverage says whether that piece survived.
What the music hall is designed to be
With the hall shifted east, its doors and terrace face the campus. The interior renderings came out Sept. 18. They show a large stage with three seating levels: a floor area, elevated seats, and an upper balcony. The lobby has a main bar, a second smaller bar, and a gift shop. An outdoor terrace looks over the campus open space, where the renderings place a second stage near the United Center. The developers say they "aren't trying to build a smaller arena." The scale fits that. The hall holds 6,000. The United Center next door seats 23,500.
Danny Wirtz, chairman and CEO of the Chicago Blackhawks and co-chair of the United Center Joint Venture, connected the venue to the block's past in a statement reported by Block Club:
"My great-grandfather, Arthur, put Miles Davis and Ella Fitzgerald on a stage at the Chicago Stadium in 1959, just two blocks from United Center. Led Zeppelin played four nights on that same block in 1977."
The plans say the hall will open directly onto the campus. Restaurants and shops will sit next to parks, a basketball court, and a winter ice rink. RIOS puts the rink between the music hall and the arena. Lined up, these pieces run west to east from the ground-level park at Damen to the hall's terrace, then the rink, then the arena. That is now one continuous stretch at street level. On Sept. 22, Urbanize repeated the 6,000 capacity and the 2028 opening and reported no new schedule or scope change.
The street changes that are still on paper
The project's transportation plan, filed with the city in January 2025, spells out how Phase 1 meets the surrounding streets. It calls for a northbound bike lane at sidewalk level on Damen between Adams and Madison and a protected bike lane on Adams. It also proposes closing Monroe to vehicles west of Damen. These are planned changes, not current detours. No construction-related street closure has been reported.
The same plan counts about 1,315 spaces in Lots G north, G south, and K, which are set aside for Phase 1. The two new garages replace them with 508 spaces in total. On paper, those parcels lose 807 spaces once Phase 1 is finished. That figure comes from the plan. It is not a count of what's closed on game nights this season.
Transit is the most uncertain piece. The plan says the project intends to work with the city and the CTA on a Pink Line station between Polk and Ashland near Monroe. Urbanize reported a 2034 target. At the groundbreaking, Department of Planning and Development Commissioner Ciere Boatright said the station was "coming closer to a reality." No construction commitment has been reported. For residents who already get around the West Loop mostly on foot, by bike, and by train, the car-light routes they use today stay the same until any of this is built.
The long clock behind the first phase
At full build-out, the 1901 Project calls for 9,463 homes, along with up to 1,309 hotel keys, 660,000 square feet of office, and 670,000 square feet of retail. Block Club's groundbreaking story put 1,893 of those homes in the affordable category. None of the housing is in Phase 1. The city's master-plan presentation estimates these completion years by subarea:
- Subarea A: 2028
- Subareas B and C: 2031
- Subarea D: 2034
- Subarea E: 2037
- Subarea F: 2040
The same presentation warns that dates and phasing may change with market needs. Of those dates, only 2028 has buildings under construction behind it, with the music hall, the hotel, and the first garages targeted then. No delivery date has been reported for the ground-level park. The Fulton Market corridor has also been moving toward walk-in, street-facing places to the east. Under the revised plan, the United Center campus's first public space will be at street level, on the corner of Damen Avenue and Adams Street.
Big projects tend to change between the renderings and the ribbon cutting. If you own near the western edge of the West Loop and want to know how the 1901 Project's build order might affect your block, Cadey O'Leary Collection follows these filings closely. Work with Cadey and start the conversation.